The Boßler Tunnel is a railway tunnel on the Wendlingen–Ulm high-speed railway. It is built as two parallel single-track tunnels between the mark.Bahnprojekt Stuttgart Ulm: MotionRide (…). Video about the planned railway line, February 2010, Position 2:09. The tunnel runs between Aichelberg and Mühlhausen im Täle under the Roter Wasen and the Boßler mountain. It is one of a series of tunnels underneath the Swabian Jura range. It is the longest tunnel on the line and the fifth longest tunnel in Germany (after the Landrücken Tunnel, the Münden Tunnel, the Filder Tunnel and the Katzenberg Tunnel).

Route

The western portal (portal Aichelberg, ), situated northeast of Weilheim an der Teck, is the border of one of the line's planning sections. The line approaches this portal from the west, parallel to the A8 motorway.

The tunnel runs in a straight line towards the southeast, passing under the Roter Wasen and the Boßler.Hany Azer, B. Engel: Stuttgart 21 und NBS Wendlingen–Ulm. In: Tunnel, Heft 7/2009, , S. 12–24 (PDF, 290 kB).Peter Marquart: Die Geologie weist ihren Weg – Tunnelbau in den Gebirgsformationen rund um Stuttgart und auf der Schwäbischen Alb. In: geotechnik, 27 (2004), Nr. 2, S. 99–103, . The tunnel climbs about to the southeast portal, with a gradient of about 25% (1 in 40). The maximum overburden depth is .

The eastern portal (portal Buch im Filstal, ) is situated between Mühlhausen im Täle and Wiesensteig. The line exits the portal onto the Fils Viaduct across the A8.

History

Deciding between alternative routes The tunnel is part of the Albaufstieg section of the line (track section 2.2), which involves an ascent of the Swabian Jura (also known in German as the Alb). 25 alternative routes were initially considered for this section.Planfeststellungsbeschluss gemäß § 18 Allgemeines Eisenbahngesetz (AEG) für die Aus- und Neubaustrecke Stuttgart – Augsburg Bereich Wendlingen – Ulm Planfeststellungsabschnitt 2.2, Albaufstieg km 39,270 – km 53,834 (PDF; 1.3 MB). Stuttgart, 20. September 2011, S. 68, 78. A plan drawn up in 1993 included an tunnel.Anonymous: Geplante Tunnel im Zuge der Neubaustrecke Stuttgart–Ulm. In: Tunnel, Volume 5/1993, , S. 288–292. A later, 1995 plan included an tunnel.Deutsche Bahn AG, Regierungspräsidium Stuttgart (Hrsg.): Ausbau- und Neubaustrecke Stuttgart–Augsburg. Abschnitt Stuttgart–Ulm. Bereich: Wendlingen–Ulm. 1. Ausgabe August 1995, Planungsstand von August 1995. Many alternative routes were considered for the Aichelberg to Widderstall corridor. As well as routes involving a combined rail and motorway tunnel and a direct route, local variations of the route in the Neidlingen, Wiesensteig and Westerheim districts were also considered.Peter Marquart: Die Entwicklung des Projektplanung. In: Regierungspräsidium Stuttgart (Hrsg.): Projekt Stuttgart 21 und NBS Wendlingen – Ulm: Die Berücksichtigung der Wasserwirtschaft in der Planung – eine Zwischenbilanz. Tagungsband, 26. September 2006, (PDF, 8 MB), S. 6–13.

The spatial planning provisions required to consider possible alternative routes for the Albaufstieg. Eight different routes were examined in detail. In 1999 a hydrological evaluation of these variants was conducted. After a planning stop in 2000, a new integrated assessment was carried out in 2006 in the context of paths for combined traffic routes.Helmut Kobus: Die Entwicklung wasserwirtschaftlicher Probleme im Planungsprozess. In: Regierungspräsidium Stuttgart (Hrsg.):Projekt Stuttgart 21 und NBS Wendlingen – Ulm: Die Berücksichtigung der Wasserwirtschaft in der Planung – eine Zwischenbilanz. Tagungsband, 26. September 2006, (PDF , 8 MB), S. 14–27. In the middle of 1991 an early road design proposed the beginning of the tunnel already in Weilheim an der Teck.Deutsche Bundesbahn, Projektgruppe NBS der Bahnbauzentrale (Hrsg.): Information Ausbau- und Neubaustrecke Stuttgart – Augsburg. Zwölfseitiges Leporello, Stuttgart, Juni 1991. while a length of 9 km was allotted for this part of Albaufstieg. According to the planning status of 1993, an tunnel was provided in this area.

As of 2004 and 2007, the planned length was . Plans of 2007 envisaged the building of an exploratory tunnel within the cross-section of the later final tunnel due to the prevalent geological conditions.Wolfgang Feldwisch: Großprojekte der Bahn als Herausforderung für den Tunnelbau. In: Geotechnik, 30 (2007), Nr. 4, , S. 217–225.

In mid-August 2009, the consultation process for the zoning section Albaufstieg to which the tunnel belongs, was completed by the regional council of Stuttgart and handed over to the Federal Railway Authority for final approval. In the process leading to approval, 82 public agencies were consulted, and 1150 private reservations were handled. The principal resulting changes affected the site logistics. In: Der Teckbote (Onlineausgabe), 22. August 2009. In mid-2009, construction work was scheduled to start in 2010.

Dispute on use of tunnel boring machines Due to the unstable rock,German original: "druckhaftes Gestein", proposed translation as "squeezing or swelling rock", roughly equivalent to the designation "very poor rock" in the RMR geomechanic system (Arild Palmström, The New Austrian Tunnelling Method (NATM), Conf. on Fjellsprengningsteknikk, Bergmekanikk, Geoteknikk, Oslo 1993, pp. 31.1 – 31.20) planning decisions initially ruled out the use of tunnel boring machines. However, according to entrepreneur Martin Herrenknecht their use could save 70 to 100 million euros over the originally tendered conventional methodKonstantin Schwarz: Herrenknecht greift die Bahn-Planer an. In: Stuttgarter Nachrichten, Nr. 185, 11. August 2012, S. 22 (online). The company obtained expert opinion at their own cost, and thus achieved the approval of mechanical tunneling. Together with the excavation of Filder tunnel, 80 to 100 million euros could thus been saved.Martin-Werner Buchenau: Die Bahn ist immer noch wie eine Behörde. In: Handelsblatt. Nr. 241, 12. Dezember 2012, , S. 18. A section was advanced using tunnel boring machines (TBM) in both tubes. Although Deutsche Bahn had stipulated conventional shotcrete tunneling in the tender documents, alternative proposals for TBM excavation were welcomed. This proved an economic solution.

Award of contract On 8 November 2011, the tunnel shell of Boßler- and Steinbühltunnel was put out for tender in Europe. The Boßlertunnel construction was subdivided into two lots of approximately and approximately in length; the Steinbühltunnel forms a third, independent lot. The contract also involved around 1.32 million cubic meters of excavated material or to be used during the project or disposed of, and the construction of four temporary connection points on the Autobahn 8D-Frankfurt: Bauarbeiten für Tunnel. Dokument 2011/S 214-349672 vom 8. November 2011 im Elektronischen Amtsblatt der Europäischen Union.

The calculation documents were sent to bidders in February 2012.Volker Kefer: Stuttgart 21 und NBS Wendlingen-Ulm Unterlage für den Prüfungs- und Complianceausschuss (PCA) der DB und den Lenkungskreis (LK) S21. Berlin/Stuttgart, 23. März 2012 PDF, (880 kB), S. 28. The contract was awarded in October 2012, together with the Steinbühltunnel construct. The cost for both tunnels came to 635 million euros, believed to be significantly below the planned cost Bahn vergibt auf der Neubaustrecke Wendlingen–Ulm die Tunnelbauwerke des Albaufstieges (PDF; 139 kB). Presseinformation der Deutschen Bahn vom 17. Oktober 2012. Originally, the award was not expected to be made until the end of 2010 (Status: December 2011).Kommunikationsbüro Bahnprojekt Stuttgart–Ulm (Hrsg.): Steckbrief: Zum weiteren Projektfortschritt im Nachgang zur Volksabstimmung . Presseinformation vom 2. Dezember 2011. The award was officially published at the end of November 2012. The total cost for both the tunnel Albaufstiegs specified end of October 2013, about 1.05 billion euros. For the full planning approval section 2.4, the price was estimated at EUR 1,074.3 million. When the financing agreement for the new line was concluded in April 2009, the Boßler Tunnel was estimated to have shell costs of around EUR 19.5 million per kilometer and tube. When applying for the financial construction permit in 2010, the planned cost was EUR 32.0 million per kilometer and tube.Deutscher Bundestag (Hrsg.): Antwort der Bundesregierung auf die Kleine Anfrage der Abgeordneten Winfried Hermann, Dr. Anton Hofreiter, Dr. Valerie Wilms, weiterer Abgeordneter und der Fraktion BÜNDNIS 90/DIE GRÜNEN – Drucksache 17/4001 – Aktuelle Entwicklungen bei der geplanten Neubaustrecke Wendlingen–Ulm (PDF; 107 kB). Drucksache 17/4293 vom 17. Dezember 2010.

Construction

The clearing work for the construction side began in early December 2012. In 2013, an embankment was added between the existing bridge over the L1214 road and the future tunnel portal.Arnd Woletz: Vorboten der Mammut-Baustelle. In: Neue Württembergische Zeitung, 8. Dezember 2012 (). The bridge was completed the first building of the new line in 2011 In early 2012, following the site survey the advance was scheduled for mid-2013 Andreas Pflüger: Mitte 2013 beginnt das große Bohren und Buddeln. In: Stuttgarter Zeitung, Nr. 24, 30. Januar 2012. The excavation at 'intermediate attack Umpfental' 'began in July 2013. 66 months are provided for the shell. The two tubes should be first built using the NATM. To accelerate the construction, three intermediate points were provided. As part of a plan amendment process in 2008 an intermediate advance was rejected.Beim Lärmschutz bleibt die Bahn unbeweglich. In: Göppinger Kreisnachrichten, 14. November 2008. The planning of 2009 envisaged another intermediate advance in the form of a preliminary window tunnel, to be filled in after completion of the tunneling. The machine advance from the western portal was over a length of . An advance from the eastern portal was not undertaken, due to the very steep flanks and environmental considerations. By mid-November 2014, 600 meters of intermediate advance had been completed.

Of the west tube, are being advanced in traditional drill and blast methods; portal structures are planned for the remaining . Of the east tunnel, are being advanced using traditional drill and blast methods and using cut and cover for the portals. Together with the Steinbühltunnel, a total of 4.3 million cubic meters of material will be excavated. The machine advance should, according to the planning status of the end of 2013, begin not later than 21 September 2014.[well, did it?]

Approximately 8,000 people attended a Construction Site Open Day on 8 November 2014. Machine advance began symbolically. The actual machine advance was scheduled to begin in January 2015.

After the overburden proved more solid than initially planned, in 2014, an extended machine advance was considered. Could machine advance be used? Spätestens am 8. Dezember 2014 wurde der konventionelle Vortrieb ohne Angabe von Gründen gestoppt. Dabei waren bergabwärts und bergaufwärts bei . It was downhill and uphill at The according to other sources for before Christmas in 2014 announced propelling start was delayed, according to web information indefinitely due to necessary fine adjustments to the machine.

At the end of February 2015, the Federal Railway announced its intention to extend the machine advance In early March 2015, talks were held between German railway and contractors on the extension of mechanical tunneling Due in part to lack of permits, the start of driving was delayed four months in total