The Addis Ababa–Djibouti Railway (; , , ) is a standard gauge international railway that serves as the backbone of the new Ethiopian National Railway Network. The railway was inaugurated by Prime Minister Hailemariam Desalegn on January 1, 2018. It provides landlocked Ethiopia with access to the sea, linking Ethiopia's capital of Addis Ababa with Djibouti and its Port of Doraleh. More than 95% of Ethiopia's trade passes through Djibouti, accounting for 70% of the activity at the Port of Djibouti.

The total railway capacity is 24.9 million tonnes of freight annually. Traffic was project to reach 6 million tonnes annually by 2023, but in 2025 it handled only 3.2 tonnes. Although infrastructure to connect the railway to the Port of Doraleh was not completed by the completion of the initial segments, they were constructed over the next several years, with the goal of expanding the annual cargo handling capacity from 6 to 14 million tonnes, with the aim of reaching 10 million tonnes of cargo by 2022.

In 2019 the railway transported 84 073 passengers and generated US$1.2 million in revenue from that service, less than in 2018. In 2019 the railway generated US$40 million in both passenger and cargo revenue, far below the operating cost of US$70 million. During the first half of 2020, the railway transported 0.7 million tonnes of freight.

Railway Operator The railway line is jointly owned by both the Djiboutian and Ethiopian governments. In Ethiopia, the state-owned Ethiopian Railway Corporation represents the owner of the railway.

The Ethio-Djibouti Standard Gauge Rail Transport S.C., a bi-national public company headquartered in Addis Ababa, was formed in 2017 to operate the railway. It is owned by the governments of Ethiopia (75% share) and Djibouti (25% share). Ethiopia holds the CEO post, represented through the Ethiopian Minister of Transport. The company currently occupies an administrative role, but it will take over railway operations at the beginning of 2024.

Through 2023, all operations on the new railway will be undertaken jointly by the China Railway Group Limited (CREC) and the China Civil Engineering Construction Corporation (CCECC). During this time, the companies will train local employees so that they can take over railway operations at the conclusion of the initial operation period. The Ethiopian Railway Corporation has also established the African Railway Academy in Bishoftu to graduate rail engineers.

Route The Addis Ababa–Djibouti Railway runs roughly parallel to the old metre-gauge Ethio–Djibouti Railway for most of its length. However, the standard-gauge railway is built on a new, straighter right-of-way that allows for much higher speeds. New stations have been built outside city centres, and most of the old railway stations have been decommissioned. There are 68 viaducts and bridges, comprising 3% of the railway's total length. There are no tunnels.

The total length of the railway line is , of which run between the two terminal stations at Sebeta and the Port of Doraleh. The remaining five kilometers are for shunting operations. A total of of the railway line is in Ethiopia, while a total of is in Djibouti. The section from Sebeta to Adama is the only double-track section of the line, and it also has the highest grades with a net elevation loss of 650 meters. It features several viaducts with lengths of up to 800 meters. The remainder of the railway is single-track, with passing loops distributed evenly along its length.

The railway begins at Sebeta, just outside of Ethiopia's capital of Addis Ababa. The city is served by two stations in its southern outskirts, at Furi-Lebu and Indode. The line then runs southeast to Modjo and Adama, both towns located in the Ethiopian Great Rift Valley. At Modjo, a railway junction exists for the planned Modjo–Hawassa Railway. In addition, at Modjo the railway is connected to the Modjo Dry Port, Ethiopia's most important inland dry port and also Ethiopia's main hub for domestic and international freight services.

At Adama, the railway turns northeast towards Dire Dawa. At Awash, there is a junction with the Awash–Hara Gebeya Railway, which is under construction as of 2018. Directly after Awash station, the line crosses 60 meters above the Awash River canyon over a 155 meter long bridge, the main bridge of the railway. The railway then proceeds to Dire Dawa, where it turns and heads directly for Djibouti. Crossing the Ethiopia-Djibouti border between Dewale and Ali Sabieh, the line reaches the Djibouti passenger terminal at Nagad railway station, near Djibouti–Ambouli International Airport. Freight trains continue the last to the Port of Doraleh on diesel power.

Stations

There are 21 dedicated railway stations along the railway; all of them can serve as passing loop stations, as they have three tracks or more (except the Adigala station which has only two tracks). Four of the 21 railway stations are designed as passing loops only, so there is no freight loading / unloading or passenger service. Two of the remaining 17 stations are freight yards only and two others will be for passengers only. The remaining 13 stations can handle both passenger services as well as freight loading / unloading.

The 15 passenger stations usually have a single boarding platform, with a station building attached to it. The platforms are about 200, 300, or 400 meters long. The Awash station, the only one with three platforms, is also located along the railway but also at the junction point with the Awash–Hara Gebeya Railway. The Furi-Lebu and Dewale stations have two platforms. All station buildings along the line contain facilities for ticketing and refreshment, and they even have prayer rooms. The architecture of the station buildings (except that of Awash station) is eclectic, featuring traditional Ethiopian elements with some Chinese interpretation.

Specifications

The Addis Ababa–Djibouti Railway was based on the Chinese National Railway Class 2 Standard. However, some changes were made at the request of the Ethiopian Railway Corporation. Ethiopia is not a member of the Northern Corridor Integration Project, which has selected the Chinese Class 1 standard for all of its railways.

Gauge: Standard gauge Couplers: Janney AAR Brakes: Air Electrification: Overhead catenary 25 kV AC / 50 Hz Target speed (passenger): Target speed (freight): Maximum train load (freight): gross Designed transport capacity: 20 million tonnes annually Gross transport capacity: 24.9 million tonnes annually (taking double-track sections into account) Minimum railway curve radius: ( at difficult locations) Maximum (ruling) gradient:1.85% (1 in 54) Length of arrival & departure track at passing loops: 850 m (dual locomotive: 880 m) [resulting max. train length ~800 m] Maximum vehicle loading gauge height: 5300 mm width: 3400 mm Trains run on the: Left Railway signalling & train protection system: automatic block signaling & ETCS-2 SIL4 Level crossings: permitted (no full grade separation) Double-stack ISO containers = 2 x 2.4m or 2 x 2.9m (unknown).

The operators of the railway consider an annual freight tonnage that is far below the railway limits. As a rule of thumb, the operators foresee an annual freight tonnage increase of about one million tonne per year, starting at 1–2 million tonnes in the first year of operations.

Although road traffic in Ethiopia drives on the right, trains drive on the left in the double-track sections. This is consistent with Chinese railway practice. The single-track sections are equipped with passing loops, each of which is triple-track so that two trains can wait for the main line to clear. Each station also serves as a passing loop.

The railway line is almost fully electrified. Power is transmitted at 230 kV and 130 kV to eight substations. Traction power is supplied at 35.8 km intervals, with 18+1 stations in Ethiopia and three in Djibouti. General electrification ends after the Djibouti–Nagad passenger station. Trains are pulled by diesel locomotives to reach the Port of Doraleh and cargo terminals at inland dry ports. This is necessary to avoid interference between the overhead catenary and loading cranes.

Rolling stock

The rolling stock is allocated from the National Railway Network of Ethiopia.

All the rolling stock had been purchased by Ethiopian Railways Corporation (ERC). All the rolling stock has been transferred to the Ethio-Djibouti Standard Gauge Railway Share Company (EDR) which operates the railway as a share kind contribution by ERC. EDR owns these rolling stocks. EDR is also expected to procure additional rolling stocks to expand its operations. Djibouti did not buy any rolling stock, and even shunting operations at Djibouti's Port of Doraleh will be performed by EDR rolling stock and EDR personnel. Djibouti chose to pay its share on railway construction instead of buying vehicles.

Handover After six years of operating, control of the railway was transferred from the Chinese Railway Construction Corporation to a joint operating agreement between the Ethiopian and Djiboutian governments.

History

Construction began in 2011 and was largely complete in 2016, but final testing continued through 2017. The line was formally opened for commercial operations on 1 January 2018.

Decline of the metre-gauge railway The Addis Ababa–Djibouti railway supersedes the Ethio-Djibouti Railway, a metre-gauge railway that was originally built by the French from 1894 to 1917, which for some time in the 20th century was the only way to reach Ethiopia from the outside world. As the railway deteriorated in the 1980s due to a lack of spare parts and maintenance, Addis Ababa lost railroad access to the sea by 2004. Rail service ran between Dire Dawa and Djibouti City until 2010 and then again from 2013 to 2014. Since 2014, operation has only been possible on 213 km of rehabilitated tracks in Ethiopia between Dire Dawa and the border with Djibouti at Guelile. The connection between the commercial centres of Ethiopia (e.g. Addis Ababa) and the sea ports in Djibouti had been broken.

Construction (2011–2016)

At that time, Ethiopia initiated an ambitious Growth and Transformation Plan (GTP) to develop the country's economy through infrastructure investment. A new electrified standard gauge railway was expected to reduce cargo transit times from three days by road to twelve hours by train, and cargo transport costs to one-third of the cost of road transport. In 2011, the Ethiopian Railway Corporation (ERC) awarded contracts for railway construction from Addis Ababa to the Djibouti border to two Chinese state-owned companies, the China Railway Group (CREC) and the China Civil Engineering Construction Corporation (CCECC).

The stretch from Sebeta to Mieso was awarded to CREC, and the section from Mieso to the Djibouti border was awarded to CRCC. In 2012, Djibouti selected CRCC to complete the final 100 km to the port of Djibouti. The total costs of the railway amounted to US$1.873 billion for the Sebeta-Mieso section, US$1.12 billion for the Mieso–Dewele section and US$525 million for the Dewele–Port of Doraleh section.

In 2013, loans totalling US$3 billion were secured from the Exim Bank of China, with US$2.4 billion going to the Ethiopian section of the railway and the balance to be spent in Djibouti. Additional funding was secured from the China Development Bank and the Industrial and Commercial Bank of China. 20,000 Ethiopians and 5,000 Djiboutians were hired for construction work. Track-laying was completed on the Mieso–Djibouti segment of the project in June 2015.